GAZPROMNEFT-Moscow Refinery


Site: Omsk; 


Customer: Gazpromneft-Omsk Refinery


Project Delivery Timelines: 2009-2021


Service Package: engineering, EHT system delivery, construction, installation, supervised installation, commissioning


Facilities:

- Advanced Oil Refining Complex. Sulfur recovery unit and offsites. Waste water precipitator. 6/0.4 kV transformer substation. Packaged modular building

- Installation of EHT systems for air cooler steam process pipelines. Combined oil refining unit (Euro+) at GAZPROMNEFT-Moscow Refinery

- Circulating water supply unit (БОВ-8а)

- Advanced Oil Refining Complex. Chemical water treater

- Installation of EHT systems for interconnections between process plants at GAZPROMNEFT-Moscow Refinery

- Sulfur recovery unit and offsites. Waste water precipitator in the Advanced Oil Refining Complex

- Active sludge plant, sulfur-alkaline sewage plant, circulating water supply unit БОВ-6, MTBE plant, atmospheric and vacuum distillation unit (АВТ-6), PSA unit, environmental monitoring system

- Revamp of Г-43/107 catcracker

- Gas fractionator 2 cum reflux treater (H2S, mercaptan sulfur)

- Standardization of heater performance of ЛЧ-35/11-1000 Plant in Shop 2

- Hydrogen unit, bitumen unit, nitrogen unit

- Isomerization plant

- Chemical water treater. Roof heat tracing

- Daelim. Advanced Oil Refining Complex. Heat tracing of hydrocracker and H2 unit buried piping

- Dedicated flare system 2

- Site 4137.06 – Liquid nitrogen storage